Location
Anticipated completion date
May 2025
Work Begins
Mon. to Fri.
Project Details
Washington Water Service has contracted with Terraphase Engineering and Bison Well Drilling to complete a new groundwater well on the Bucklin System. This project will begin in early March and will be ongoing until June.
The project will be contained within the wellsite property. During construction, you will see crews on site and work vehicles moving in and out of the property. You will notice construction noise in the work area while crews are on site each day. Work will begin at 8:00 a.m. and should be wrapped up each day by 5:00 p.m., Monday through Friday, barring any emergencies. Work vehicles and equipment will be parked on-site and will not impact access along NE Bucklin Hill Road; however, residents should plan for extra time and pay attention to where crews are working, to allow safe access around the work site. Please avoid the work area when possible.

Current Projects
-
Final Phase—Ranch Acres Water Mainline Replacement
Location
115th Lane SE and Laukers Lane SEAnticipated completion date
December 2026 -
Corrosion Control Plant, S&I System
Location
72nd Avenue NW between 99th Street Court NW and 98th Street Court NWAnticipated completion date
April 2027 -
Iron, Manganese, & Arsenic Removal System, Foss Rd
Location
22389 Treefarm Ln NE, Poulsbo, WA 98370Anticipated completion date
November 2026 -
Pederson Harold Wellsite and Pumping Upgrades
Location
13818 Purdy Drive NWAnticipated completion date
November 2026